Incident at Onitsha Sub-Region Not Explosion as Claimed By EEDC- TC
The Transmission Company of Nigeria has stepped in to correct the alleged misinformation recently published by Enugu Electricity Distribution Company PLC (EEDC) on August 27, 2025, regarding the cause of the power outage in Anambra State and Oji River in Enugu State.
According to the TCN, contrary to EEDC’s claim, there was no explosion at its (TCN) station at Onitsha Sub-Region.
Explaining further, the TCN stated that, ” The actual cause of the partial loss of power in the 330kV switch yard at Onitsha Sub-Region, which occurred on August 21, 2025, at about 02:34 hours, was an insulation flashover of porcelain insulator (P1) of the red phase jumper conductor to bus bar 1 due to rainfall.
” The power was later restored at 17:54 hours the same day. Notably, TCN had planned a scheduled outage on August 31, 2025, and September 1, 2025, to replace the stack porcelain insulators.
TCN stressed that there was no explosion of equipment or loss of switchgear equipment in the TCN Onitsha region.
” We urge EEDC to ensure the accuracy of information disseminated to the public, as deliberate deception or propaganda is unprofessional and unacceptable,” stated TCN in its statement signed by Mrs Ndidi Mbah, the company spokesperson and released Thursday.