Interface Newshub
BusinessOil & Gas

TCN Sets 2- Week Target for Upgrade of Kaduna -Jos Transmission Line


…..Targets New Wheeling Capacity of 1500MW
The Transmission Company of Nigeria (TCN) will commence the final stage of the construction of its new Kaduna – Jos 330kV double circuit transmission line, with the erection of eight triple-circuit towers at the intersection point of the new double circuit and existing single circuit 330kV transmission lines, to enable the stringing of the three 330kV lines.
With this, the line will be upgraded from 500 megawatts (MW) energy wheeling capacity to 1,500MW, which is 200 percent capacity increase.
The reconstruction work is expected to be completed within eight days, from the 8th to 15th December 2021.
Consequently, there will be power outage on the 132kV Zaria- Kaduna transmission line, 33kV Turunku, and part of the 33kV Jaji feeder, from 8 am to 5 pm daily for the eight days indicated, to ensure a safe working environment for the execution of the reconstruction work. On completion, the new 330kV double circuit transmission lines will increase the total capacity of the Kaduna – Jos line from 500MW to 1500MW.
Meanwhile, TCN has made arrangements to continue to supply bulk electricity to Jos Distribution load centers in Jos, through the Makurdi 330kV lines 1 and 2, to minimize the effect of the capacity upgrade and assure that the project will be completed on the 15th of December as scheduled.
The decision to reconstruct and upgrade the Kaduna -Jos SC transmission line was due to the fact that the line is overloaded and can no longer cope with the load profile in that axis. The completion of the new 330kV Kaduna- Jos DC transmission lines will resolve the present and anticipated increase in load demand on the line route.
TCN’s use of multi-circuit towers in some locations will prevent the demolition of properties in heavily built-up areas and still achieve increased bulk transmission capacity along that line route. We will therefore dismantle and reconstruct eight (8) no existing single circuit towers into special triple-circuit towers.
We regret any inconvenience the load shedding may cause electricity customers affected by the reconstruction works on the line and note that the increase in capacity to 1500MW will positively impact voltage stability on the axis. Bulk power transmission will be restored immediately after reconstruction work is complete.

Related posts

SEPLAT Q1 Results: $28 million PBT, Revenue Up by 16.8%

Dayo Omoogun

New Awards to NCC, Danbatta Underscore Significance of Telecom Contribution to GDP

Dayo Omoogun

More Awards Roll in for NCC for Regulatory Effectiveness

Dayo Omoogun

Leave a Comment