The Transmission Company of Nigeria (TCN), Kano Region, and the Kano State Ministry of Land and Physical Planning have reached a pivotal agreement to resolve legal disputes that had stalled the Kumbotso–Rimin Zakara 330kV transmission line project.

The meeting, held on July 21, 2025, was convened by the Ministry to address litigation surrounding land ownership and compensation, which had significantly delayed progress.

Under the terms of the agreement, the Kano State Government will compensate individuals whose cases remain under legal consideration and provide alternative land to affected parties. This resolution removes the final obstacles to the project’s completion.

TCN is optimistic that the agreement will accelerate work on the transmission line, which is critical to improving electricity infrastructure and supporting industrial development in the northern parts of the nation. The development is a major breakthrough in the ongoing efforts to further strengthen the national grid.

Related posts

Ondo Church Kidnapping: CAN Disowns Pastors

Dayo Omoogun

NDC Commandant Commends FCT Minister On Infrastructure, Security

Dayo Omoogun

MRA to Gov Mbah: Respect Press Freedom, Stop Intimidating Journalists 

Dayo Omoogun

Leave a Comment